Arvind Sylva Construction Status
Arvind Sylva construction status: the project is newly launched and K-RERA approved (registration PR/090726/008800, granted 09 July 2026). The official launch took place on 09 July 2026 and the EOI window has closed. Site mobilisation and sub-structure works are scheduled to begin in September 2026 per the RERA construction schedule. Proposed completion is 31 August 2031 and possession is targeted for December 2031. This page covers the full milestone calendar, the current site status and what to expect at each build stage.
Project Status Snapshot — As of July 2026
| Status Item | Detail |
| Current stage | New Launch |
| Karnataka RERA | Approved (PR/090726/008800) — granted 09 July 2026 |
| Official launch date | 09 July 2026 |
| Site mobilisation | Q3 2026 (post-launch) |
| Sub-structure (earthwork, foundation, basements) | Sep 2026 – Oct 2027 |
| Foundation completion | Q2 – Q3 2027 |
| Super-structure (RCC + masonry) | Aug 2027 – Sep 2029 |
| Finishing, MEP & external works | 2028 – Aug 2031 |
| Proposed completion (RERA) | 31 August 2031 |
| Handover / possession | December 2031 |
Current Site Status — June 2026
Geo-tagged site photographs from the Karnataka RERA filing show the current pre-construction stage — a cleared, levelled plot on Sarjapur Road at the project coordinates (12.8983, 77.7173), with the borewell and survey markers in place as site mobilisation begins ahead of sub-structure works from September 2026.
25 June 2026 — cleared, levelled plot on Sarjapur Road (12.8983, 77.7173). Source: K-RERA filing.
24 June 2026 — borewell and survey markers as mobilisation begins (12.9000, 77.7174). Source: K-RERA filing.
Full Milestone Calendar
Launch & RERA Approval — 09 July 2026 (Current stage)
- Karnataka RERA registration granted — PR/090726/008800 (09 July 2026)
- Official launch on 09 July 2026 with confirmed pricing, inventory and Agreement-to-Sale templates
- EOI window closed at launch; the refundable ₹5–6 Lakh reservation had locked in the ₹18,335/sq.ft. launch rate for early applicants, who now convert to formal allotment (10% milestone payment, less EOI)
- Bank-loan disbursement panel activated (HDFC, ICICI, SBI, Axis, Kotak, PNB, Bank of Baroda, LIC Housing)
- Kodathi Experience Centre operational with 3 BHK and 4 BHK model apartments (9 AM – 7 PM daily)
Site Mobilisation — from September 2026 (Upcoming)
- Site office and contractor camp set up; survey markings and gridding finalised against the master-plan layout
- Tree-preservation, landscape survey and geotechnical/soil-test reports archived
- Boundary wall, approach-road work, earthwork and site levelling scheduled to commence per the RERA schedule (from 01 September 2026)
Sub-Structure: Earthwork, Foundation & Basements — Sep 2026 to Oct 2027
- Earthwork and site levelling (Sep 2026 – Feb 2027); foundation footing (Dec 2026 – Mar 2027)
- Work up to plinth level (Jan – Apr 2027) and retaining walls (Dec 2026 – Mar 2027)
- Two basement levels and parking floors cast for all four towers (Mar – Oct 2027)
- Excavation and foundation milestone payments due from buyers (~10% each)
Super-Structure: RCC & Masonry — Aug 2027 to Sep 2029
- RCC framed structure and masonry construction for all four towers (28 Aug 2027 – 30 Sep 2029)
- Slab-by-slab vertical rise to 2 Basement + 17 floors (G+17), ~59.95 m tower height
- Basic water-supply, sanitary and electrification rough-in runs in parallel (Mar 2027 – Mar 2030)
- Slab milestone payments billed at 1st, 10th, 20th and final slab stages
Finishing, MEP & External Works — 2028 to Aug 2031
- Plastering (Aug 2028 – May 2030); dadoing, skirting, flooring and tiles (Sep 2028 – Nov 2030)
- Joinery — doors, windows, ventilators (Dec 2028 – Oct 2030); railings and grills (Aug 2028 – Aug 2029)
- Painting (Feb 2029 – Feb 2031); electrical, water-supply and sanitary finishing (Apr 2029 – Mar 2031)
- Weather-proofing (to Dec 2029), fire-fighting systems (to Jun 2030), lift commissioning, DG/HT power and the sewage treatment plant
- Elevation / façade works (Sep 2029 – Oct 2030); internal and external works including landscaping (Jul 2030 – Aug 2031)
- Clubhouse fit-out and vehicle-free podium landscape completion; brickwork and flooring/fittings milestone payments due (~10% each)
- Proposed completion (RERA): 31 August 2031
Handover — December 2031
- Occupancy Certificate (OC) obtained from BDA
- Snagging walkthroughs with buyers and punch-list corrections
- Final 5% milestone payment plus statutory charges (GST, stamp duty, registration)
- Apartment Owners' Association handover and key collection
How to Track Progress
- Site visits: Open to prospective and confirmed buyers via the Kodathi Experience Centre — 9 AM – 7 PM daily.
- Construction updates: Quarterly emailers sent to booked buyers with photographs of build progress.
- Construction status dashboard: Watch this page — milestones are updated as they're certified by the project engineer.
- Karnataka RERA portal: Post-registration, buyers can view quarterly progress reports on the K-RERA portal under the project's registration number.
Frequently Asked Questions about Construction Status
1. What is the current status of Arvind Sylva?
The project is newly launched and K-RERA approved. Karnataka RERA registration is approved (PR/090726/008800). It is granted on 09 July 2026. That is ahead of the official launch on 09 July 2026.
2. When does on-site construction start?
Active site mobilisation begins in Q3 2026 immediately after the official launch. Excavation and piling for all four towers run from Q4 2026 through Q1 2027.
3. When will the towers reach full height?
All four towers are scheduled to reach their full 2 Basement + 17 floor (G+17) structural height by end of 2029. Finishing works run from 2030 through Q3 2031.
4. When is handover scheduled?
Handover and possession are targeted for December 2031, after the Occupancy Certificate is obtained from BDA and snagging walkthroughs are complete.
5. Can I visit the site during construction?
Yes — EOI applicants and booked buyers can visit the Kodathi Experience Centre at any time (9 AM – 7 PM daily). Once on-site construction begins, the centre will include a viewing deck over the active build zone.
6. How are construction-linked payments triggered?
Each milestone payment is triggered when the corresponding stage is certified complete by the project engineer. Buyers receive an invoice along with the engineer's certification document. The milestone schedule is detailed on the payment-plan page.